Reconstruction of the garden ring earthen rampart. New hiking trails open? And you yourself know what happens in the torn streets

Everyone can see the global scale and scale of repairs and alterations - the entire center of Moscow has been dug up for more than three months, torn apart, partitioned off and clogged with all kinds of equipment. It would seem that everything could have been done on such a grand scale a long time ago, but ... the end of the work is still far away.
And the reason is so simple...

Recently, I moved to Sadovoye and every day from the balcony I can observe the progress of work on Sadovaya-Sukharevskaya - how they make nests for trees, and how cable channels are laid, and how paving slabs are laid, and how asphalt is changed at night.
Well, and, accordingly, draw certain conclusions and get an unambiguous answer on at least about one of the weighty reasons that all this has been going on for several months and will continue for at least another month. Although there good examples when a large-scale reconstruction of some streets was carried out simply at a cosmic pace with minimal inconvenience for the city, its residents and drivers.

To illustrate my findings, over the course of one day, from time to time, I took pictures from the same point of view on the construction sites where I observed the workers. Green arrows marked those who do something, red arrows marked those who kick x...and, husk seeds or just sleep.

Look at the photo below and everything will become as obvious to you as it is to me.

First location. 6 boobies. All red (do nothing), an hour or more sat and just chattered.


Second location. 7 goonies and 1 conscious digging a hole. Most of them either chatter on the phone or chatter among themselves.

Third location. 12 dummies and 2 conscious ones who lay tiles. They scratch their tongues again

The fourth location opposite side streets. Obviously a different team - and the color of the vests is different, and the approach to work is different. All 6 are working

The adjacent area is the same. Three more, all working. Looking ahead, I will say that these workers almost always, when I went out to take control pictures, worked, unlike everyone else

The fifth location is 10 meters from the previous one. Already a familiar picture - 5 hard workers scratch their tongues.

Another 10 meters to the side. Three more slackers

Another 20 meters. And 12 more slackers.

And 4 more loafers 20 meters from the previous ones.

An hour has passed. I shoot from the camera at the same locations.
At the first location, life is barely glimmering. Already two workers and both are busy with something

Four comrades slowly move from the first to the third. Looks like they need a lot of work...

Yes, there really is a crowd of people here. As many as 6 work and 14 scratch their tongues ...

Fourth location. And again everyone is working there, like an hour ago. All 7 workers.

Fifth location. Nothing changed. Four idlers against one conditionally doing something

Another two hours passed.
People appeared at the first two, two were doing something, five more were very tired and were toiling from idleness

On the third, nothing changes - there are still a lot of people and still no one does anything, all 13 people.

At the fourth location, apparently, a small smoke break. Four rest, five continue to work. They were joined by four people from the fifth location. True, they are idle, as in the previous place.

If we sum up the dry numbers, then it turns out the following:
- 35 people were seen working
- rested doing nothing 95 people, almost three times more.
I understand that people should have a break, and I fully admit that at some point I got on the resting teams. But, I repeat, I watch this construction site every day, I constantly see how a few units of workers work, and the majority play the fool, highlighting short breaks for work in this process.
At the same time, there are areas, as I said above, where people work all the time, whenever they go out to the balcony to look.

Below general plans and highlighted areas where locations are located:
to the left of Sadovoe are the first and second locations, to the right is the fifth with several points

on right hand from Sadovoye the third, on the left - the fourth with the most conscious workers.

In general, while everything is in the process on Sadovoye.
I am sure that soon it will become very beautiful here and the reconstruction is not in vain. I just wish this construction and road traffic hell would end as soon as possible...

On the night of April 22, 2017, Moscow entered a period of constant road repair which will last until October. According to the press service of the capital's mayor's office, the steady weather will allow the specialists of the complex to begin replacing asphalt on key highways of the capital.

Repair at the interchanges of the Moscow Ring Road and highways

“The planned road repair season will last until mid-October,” said Petr Biryukov, Deputy Mayor of Moscow for Housing and Utilities and Improvement. Repairs will be carried out at those facilities where the warranty period of the asphalt concrete pavement has expired. First of all, the asphalt will be changed in the straight sections and interchanges of the Moscow Ring Road. Among them are the intersections of the Moscow Ring Road with the Entuziastov Highway, Ryazansky prospect, as well as sections of the outer side of the Ring Road in the area of ​​km 4-6, km 74-76, km 104-106.

Then the road workers will move to the facilities on the Third Ring Road and the main outbound highways, as well as other streets of the city.

Work will be carried out at night with a partial restriction of traffic.

According to the agency, 18 million will be upgraded this season throughout the city square meters roadbed. Most of the work will be carried out by the State Budgetary Institution " Car roads". Its workers will repair 10 million square meters. m of asphalt.

At all sites, curb stone replacement, manhole repair, removal of the existing roadway using cold milling, laying of new asphalt and marking will be carried out.

The Garden Ring will be left without a strip for the duration of the repair

serious Men at work have already begun on the Garden Ring. The metropolitan department is responsible for them. overhaul. Landscaping began both on the inside and on outer sides Garden Ring.

Traffic on Sadovoe will be limited - depending on the work, it will be impossible to drive either one or four lanes.

At the same time, landscaping work has also begun on the Boulevard Ring and in the Yakimanskaya Embankment area. Work will continue until the end of August. In this regard, traffic will be seriously impeded in the central part of the city, and parking spaces will be eliminated during the work.

GKU TsODD

Recall that in the framework of the city improvement program, the city authorities in 2015 have already repaired 47 streets, and in 2016 - 61 highways. All major works were carried out between May and August, including the repair and expansion of sidewalks and the relocation of utilities.

The Traffic Management Center (TsODD) warns of possible traffic difficulties in the central part of the city and an increase in traffic congestion up to 8-9 points in the morning and evening rush hours.

GKU TsODD

“The main difficulties will be observed on the Garden and Boulevard rings, as well as on the streets adjacent to them. Besides, most of flow will also move to the Third Transport Ring, and therefore there may be additional difficulties in traffic on this highway, ”the TsODD said and asked motorists to travel to central part cities use public transport to save time.

The CODD assures that public transport ready for an influx of passengers. At the same time, it is not recommended to use the city center for transit trips by car - it is better to use the Third Ring Road. In order not to get stuck in traffic jams for several hours, drivers will have to carefully choose detour routes, and in order not to be late for meetings, lay additional time on my way.

Meanwhile, the mayor of the city, Sergei Sobyanin, apologized in advance to the residents of the city for temporary inconvenience on his page on the social network VKontakte.

"The most active period works, including on Boulevard and Garden. Until September, the main work will be completed. Problems with road traffic during this period will be quite serious. But in the end, we will get high-quality urban space in the city center, on its main streets, ”Sobyanin wrote.

Yesterday, the selection of most of the contractors for the reconstruction of the Garden Ring in 2017 under the My Street program was completed.

The results are surprisingly similar. They demand good analysis Let's start with the first 5 contests.

Segments 5 and 8 will be reconstructed by Technoconcept LLC, 6,7 and 9 - by ARPT JSC (which lost segments 5 and 8 to Technoconcept).

It seems that there is nothing remarkable in the competitions - everywhere there is a certain price reduction (within 5%), everywhere there are several participants - all the competitions took place.

And it would be possible to relax on this and wait for the start of work in order to take control of compliance with the rules and the project. But no, the Moscow authorities won't let us relax - wherever you go, there are violations everywhere. Not without them in this case.

Moreover, unlike the petty dirty tricks that are usually inherent in tenders for a construction site in Moscow, here people immediately committed a criminal offense. (No, there were also minor dirty tricks - the design documentation was posted in the competitions only after my complaints to the FAS.)

What is the essence of the crime? Everything is very simple - LLC Technoconcept and JSC Agency for the Development of Advanced Technologies entered into a cartel, that is, they committed a crime under Art. 178 of the Criminal Code:

Article 178. Restriction of competition

1. Restriction of competition by concluding a competition-restricting agreement (cartel) between economic entities-competitors, prohibited in accordance with antimonopoly legislation Russian Federation if this act caused major damage to citizens, organizations or the state, or resulted in the extraction of income in large size, —
shall be punishable by a fine in the amount of three hundred thousand to five hundred thousand rubles or in the amount of wages or other income of the convicted person for a period of one to two years, or forced labor for a period of up to three years with deprivation of the right to hold certain positions or engage in certain activities for a term of up to one year or without it, or by deprivation of liberty for a term of up to three years with deprivation of the right to hold certain positions or engage in certain activities for up to one year or without it.

2. The same acts:
a) committed by a person using his official position;
b) associated with the destruction or damage of another's property or with the threat of its destruction or damage, in the absence of signs of extortion;
c) causing particularly large damage or entailing the extraction of income on an especially large scale, –
shall be punishable by compulsory labor for a term of up to five years with deprivation of the right to hold certain positions or engage in certain activities for a term of up to three years or without it, or by deprivation of liberty for a term of up to six years with a fine in the amount of up to one million rubles or in the amount of wages or other income convicted for a period of up to five years or without it and with deprivation of the right to hold certain positions or engage in certain activities for a period of one to three years or without it.
Notes. 1. Income on a large scale in this article is recognized as income, the amount of which exceeds fifty million rubles, and income on an especially large scale - two hundred and fifty million rubles.
2. Large-scale damage in this article is recognized as damage, the amount of which exceeds ten million rubles, and especially large-scale damage - thirty million rubles.
3. A person who has committed a crime under this article shall be exempted from criminal liability if he was the first of the accomplices in the crime to voluntarily report this crime, actively contributed to its disclosure and (or) investigation, compensated for the damage caused by this crime or otherwise made amends for the damage caused. and if his actions do not contain other corpus delicti.
Pierced guys on trifles. They prepared perfectly - no director. neither the founders of the companies are connected in any way (at least according to open sources this relationship is not observed). However, I not only found this connection, but also documented it. Someone involved in the registration of Technoconcept LLC in the SRO of builders screwed up and indicated his work phone number there. Work phone in the office of JSC "ARPT". Look here. what number does the ARPT indicate in all its contracts for public procurement:

Since it is obvious that two structures that did not constitute a group of persons participated in the competition (which would allow circumventing the restrictions of the antimonopoly law), the presence of a carefully concealed connection between them almost unequivocally indicates collusion.

UPD. After the publication of the publication, the employees of the Anti-Corruption Foundation sent me two wonderful documents that fully confirm my conclusions:

As you can see, in both companies, the same lady, Chuguy Daria Alexandrovna, holds the leading position. Separately, it should be noted that these documents were available to the commission of the customer, that is, they knew about the existence of a connection there. Thus, the circle of participants in the crime has expanded dramatically ...

According to the procurement documentation, the participant must have “experience in the execution (taking into account succession) of the contract (agreement) for the performance of relevant construction works for the last 3 years before the date of filing an application for participation in the relevant tender or auction”, “at the same time, the cost of the previously executed contract (agreement) ) is at least 20 percent of the initial (maximum) price of the contract, agreement (lot price), for the right to conclude which the procurement is being carried out.

In the course of consideration by the Federal Antimonopoly Service of the complaint of one of the potential participants in the procurement on this requirement, the representative of the customer stated that "according to the appendix" Technical task» documentation about the Auction, the main scope of work is repair work, construction work of capital construction objects, namely repair of roofs, facades, pavement of the pavement at the expense of the roadway, repair of rainwater drainage, repair of manholes on the roadway and on the sidewalk, repair and transfer of storm gratings on the roadway, installation and repair of stairways, installation and repair of retaining walls, installation of a storm water inlet tray, installation of a side stone made of granite. Based on the foregoing, the Customer, the Authorized Body established a requirement for procurement participants to have experience in performing work on the construction, reconstruction and overhaul of capital construction facilities. »

And now we raise our eyes up and look at the date of issue of the SRO approval certificate for Technoconcept LLC. Yes Yes, 06.03.2017 , a few days before the submission of documents for the competition. He did not have any other permits, that is, the company NEVER fulfilled construction works in general, and even more so for the amount of 200,000,000 rubles, as required by participation in more than billions of dollars of competitions.

But the entire commission of the customer, Technoconcept LLC, joyfully allowed participation, and then recognized it as the winner.

Materials about all these violations will go to the Main Control Department, the Federal Antimonopoly Service and the Investigative Committee today. Contracts have not yet been concluded, there is a chance that they will not be concluded. Because when construction begins with fraud, you can be sure that it will end with disgusting quality and a waste of funds.

And Muscovites will swallow dust all summer long, and then stumble on poorly laid tiles.

It was decided to entrust the reconstruction of the Garden Ring to scammers

WHY EXPAND PAVEMENTS

- In the city, the streets were again dug up due to repairs. Muscovites are complaining.

Of course, motorists and pedestrians are concerned about the inconvenience. On the websites of the Moscow government, citizens can leave their comments (see " Feedback"). But we do landscaping not for a year, not for two, but for several decades ahead. Such global works have not been held in Moscow since the 1930s. Therefore, 2 - 3 months can be tolerated.

“Do you know what is happening on the torn streets?”

I check every day. Our employees are assigned to specific areas to control the quality of repairs. We track these works and through urban system video surveillance. Now we are going to install additional cameras so that on the website of the Moscow government mos.ru everyone can watch the renovation of the streets online.

- Why expand sidewalks at the expense of roads? There are always traffic jams...

6 - 7 years ago in Moscow it was impossible to walk along the sidewalks, especially in the center. It was impossible to drive through the streets. If you parked your car, then you couldn't get it out of those traffic jams that were gathering on the sidewalks and roads. Now we are opening sidewalks for pedestrians. Look at Tverskaya. It became more space, restaurants, verandas began to open one after another, people relax, communicate.

INSTEAD OF SELF-BUILDING - LAWNS AND STORE

This year, sites freed from unauthorized construction were included in the My Street program. As long as there are empty spaces. Near the Krasnopresnenskaya metro station, drivers park their cars on the site of a demolished restaurant.

We will carry out landscaping at all sites where the samostroy was demolished. We will plant squares, put up benches. By the City Day, we will pave the area near the entrance to the Barrikadnaya metro station with new granite tiles. Trees and bushes will appear here. At the metro station "Krasnopresnenskaya" we will break a large square with benches. We will also plant additional trees near the high-rise building. There will be no parking here.

- New hiking trails will open?

Lubyanka Square will be completely redone and connected by a single walking route with Ilyinsky Square, Staraya and new squares, Slavyanskaya Square, Kitaygorodsky passage, Varvarka and a park in Zaryadye. From the park, then it will be possible to go to the floating bridge over the Moscow River.

THERE WILL BE NO LARGE OVERLAPPINGS

- On the Garden Ring began repairs and it became even more difficult to pass.

We will cover one or two extreme strips. The now closed lanes on both sides of the road will later become a pedestrian zone. At the same time, the number of lanes will remain the same due to the narrowing of their width to the permissible - 3.25 meters (some lanes on Sadovoe are now 3.5 - 5 meters wide. - Auth.). As practice has shown, the speed of movement in the stream increases, and the number of accidents decreases.

- When will it all end?

All major work on My Street should be completed by City Day (this year it is celebrated on September 9. - Auth.). We plan to complete the installation of cable ducts, granite paving, installation of borders in July. And we will start planting trees in late October - early December. According to environmentalists, seedlings take root better this way.

- AT next year repair again?

The program is due to end in 2018. While it is being discussed whether to continue it further.


WHAT ELSE

- They say that the storm drain on the repaired streets will not withstand heavy rains again?

On some streets in the historical part of the city, there is no drainage system at all. And where it is, communications cannot physically cope. Last year we had abnormal rains and flooded the streets. Of course, we drew conclusions and monitored the existing engineering networks. This year we are laying new drainage pipelines and installing additional gratings. First of all, on the Garden and Boulevard Rings, on the embankments, in Kitaigorodsky Proyezd, next to the Zaryadye Park. At the same time, we make sure that construction waste does not get into the stormwater drain. After all, the gratings were in the area of ​​​​improvement of the streets.

SPECIFICALLY

This year, under the My Street program, 82 streets, embankments, entrances to the city and sites near the Moscow central ring. The list includes Tverskaya (from Nastasinsky Lane to Triumphalnaya Square) and 1st Tverskaya-Yamskaya Streets, Garden and Boulevard Rings, old streets near the park in Zaryadye, the museum quarter on Volkhonka, the new Khokhlovskaya Square with a preserved wall fragment white city, Tverskaya Zastava square in front of Belorussky railway station with a restored tram line.

Twelve embankments in the center of Moscow will turn into connected walking routes near the water. Among them are Krasnopresnenskaya, Goncharnaya, Prechistenskaya and other embankments.


QUESTION - RIB

Why is the tile in some places poorly laid?

Regarding the poor-quality laying of tiles, I admit that in some areas this is possible. But we respond quickly. Under warranty obligations, the contractor is obliged to correct violations at his own expense within two years.

- That is, money is not spent from the city budget for repeated repairs?

In no case. The contractor corrects all violations at his own expense under state contracts.